CMU wall work from 10-26-2011 to 10-28-2011
Instalation of CMU block on new foundations, six corses high with #4 bar steel every second course. Met with Harry from the gas company to review gas tank location and excesability.
Friday, October 28, 2011
Monday, October 24, 2011
Friday, October 21, 2011
Thursday, October 20, 2011
main house foundation concrete pour
These are the photos of the house foundation footings complete with steel set and concrete poured out on 10/19/2011