Welcome

This site was create to help everyone involved in the renovation project at 59-595 Ke Iki Road stay up to date.

Saturday, October 29, 2011

CMU wall work from 10-26-2011 to 10-28-2011








Instalation of CMU block on new foundations, six corses high with #4 bar steel every second course.  Met with Harry from the gas company to review gas tank location and excesability.

Monday, October 24, 2011

Instalation of new CMU block & steel




Instalation of new CMU block and horizontal steel in new basement walls, dated 10/24/2011

Thursday, October 20, 2011

main house foundation concrete pour









These are the photos of the house foundation footings complete with steel set and concrete poured out on 10/19/2011